The five water main replacement projects scheduled for 2020 are now complete.
All five projects involved replacing old cast iron pipe that showed severe levels of corrosion, which led to numerous water main breaks in the last 10 years. The details of each project are as follows:
W. Canyon Avenue – Located in the Columbine Hills subdivision, this project replaced 1,005 feet of 6-inch cast iron pipe in W. Canyon Avenue between S. Depew Street and W. Canyon Drive with 6-inch PVC pipe.
W. Canyon Trail – Located in the Columbine Hills subdivision, this project replaced 900 feet of 6-inch cast iron pipe in W. Canyon Trail between S. Depew Street and S. Sheridan Court with 6-inch PVC pipe.
W. Alder Avenue – Located in the Columbine Hills subdivision, this project is replaced 465 feet of 6-inch cast iron pipe in W. Alder Avenue between S. Kendall Boulevard and S. Jay Drive with 6-inch PVC pipe.
S. Kendall Boulevard – Located in the Columbine Hills subdivision, this project is replaced 1,107 feet of 8-inch cast iron pipe in S. Kendall Boulevard between W. Alder Avenue and W. Monticello Avenue with 8-inch PVC pipe.
W. Geddes Avenue – Located in the Columbine Knolls and Grove subdivision, this project replaced 1,311 feet of 6-inch cast iron pipe in W. Geddes Avenue between S. Sheridan Court and S. Chase Court with 6-inch PVC pipe.
Due to the rapidly changing state and local policies regarding COVID-19, the District did not conduct in-person Informational Pop-Ups this construction season. Communication with residents in the affected subdivisions was handled via mail, social media, or door-to-door interaction.
Final paving for these projects took place at the end of October. Due to snow and weather impacts, final clean up was delayed and contractors are still in the process of restoring the areas affected by construction.
If you have any questions or concerns pertaining to these projects, please call the District office at 303-979-2333.