S. Depew St. Project

The new water main on S. Depew St., from W. Ottawa Ave. to W. Rowland Pl., has been successfully installed and passed all required testing and inspections. All residential water services along S. Depew St. have been transferred to the new main. Crews are currently performing asphalt trench patching.

The contractor will take a two-week break before mobilizing to the Columbine Hills subdivision for the next phase of projects.

Contractors installing water pipe at W. Rowland Ave. and S. Depew St.

Contractors installing water pipe at W. Rowland Ave. and S. Depew St.

Columbine Hills Projects

W. Chestnut Ave. – This project will replace 1,453 feet of 6″ cast iron pipe with 6″ PVC pipe in W. Chestnut Ave. from S. Lamar Court to S. Kendall Blvd.

S. Jay Dr. – This project will replace 623 feet of 12″ cast iron pipe with 12″ PVC pipe in S. Jay Dr. from W. Elmhurst Dr. to W. Alder Ave.

 

If you have questions or concerns pertaining to these projects, please contact the district office at 303-979-2333 or info@plattecanyon.org.