This project rehabilitated 2,437 feet of 8-inch concrete sewer pipe located in S. Gray Ct., W. Portland Dr. and W. Quarles Dr. using cured-in-place rehabilitation, reestablished 39 service connections and will line 11 concrete manholes. The estimated cost of the project including construction, engineering and contingencies is $130,587.

 

 

 

 

For questions or comments concerning this project, please feel free to call the District’s Project and Construction Coordinator, Tony Cocozzella at 303-979-2333.

 

  CURRENT STATUSThis project completed the cured-in-place rehabilitation of the lines and reestablished the service connections. The manholes are currently being lined as the final step of the project.