Water Main Replacement Projects
S. Newland Circle
This project replaced 1,700 feet of 6-inch cast iron pipe with 6-inch PVC pipe in the S. Newland Circle loop off of W. Leawood Drive in Leawood.
W. Alder Way
This project replaced 700 feet of 6-inch cast iron pipe with 6-inch PVC in W. Alder Way between S. Depew Street and W. Alder Avenue in the Columbine Hills subdivision.
S. Depew Street
This project replaced 1,900 feet of 8-inch cast iron pipe with 8-inch PVC in S. Depew Street between S. Platte Canyon Road and W. Canyon Trail in the Columbine Hills subdivision.